Here are the steps which Walltec takes for Epoxy Injection:
​
-
Locate crack-by grinding (or) wire brushing
-
Surface mount the T’s- every 8-10 inches
-
Patch T’s and crack- continually until T’s are patched and crack is patched ( this will need 6-8 hrs to dry)
-
Following Day- flush with mild water and Phosphoric Acid Mixture ( flush debris and calcium deposits)
-
Flush with copious amounts of straight water- sometimes needs to flow out with forced air.
-
Pump Epoxy- Staring with first T until epoxy resin comes out of the next T inline.
-
Pump along crack until all Port’s/T’s are injected.
-
Clean up- Port/T’s are mechanically removed with a grinder (if needed)
-
Clean up